In August, in the Cosmopolit Traian Grozăvescu 7 construction site, intensive work was done on the facade of the building on the eastern side, which was 70% completed.

On floors 1,2,3,4 stairs A and B the plastering process and the realization of the electrical installations were completed, and on the 1st floor the primer was given.

On the 5th floor, staircase A, the plastering of the gypsum ceilings began, and on the 6th floor, both stairs, the installation of the underfloor heating system was completed, together with the process of pouring and helicoptering the related screed.

This month, in the Cosmopolitan Traian Grozăvescu 7 construction site, after the completion of the scaffolding mounting process on the eastern side, the basalt wool was assembled to insulate the buildings.

The process of making the electrical installations on the 5th floor in building A was completed, and in building B this process was completed on the 6th floor.

Also on the 5th floor, the installation of the underfloor heating system was completed, together with the process of pouring and helicoptering the related screed. The process of pouring and helicoptering the screed for the circulating terrace on the 1st floor of body A was also completed.

The plastering of the walls on the 4th floor for both buildings continues, together with the installation of plasterboard on the ceiling on the 5th floor.

This month, in the Cosmopolitan Traian Grozăvescu 7 construction site, the installation of the scaffolding on the eastern side was completed and the necessary steps for the construction of the building facade began.
On the 5th floor, the process of making electrical installations was completed, and currently work is being done on the 6th floor.
Also on the 4th floor, the installation of the underfloor heating system was completed, together with the process of pouring and helicoptering the related screed.
On the 3rd floor, in Building A, we started plastering the walls, the installation of the shoulder pads and the preparation for the installation of the window sills, and in body B, the ceiling is grouted, the plaster is sanded and the washable application.

In May, in the Cosmopolitan Traian Grozăvescu 7 construction site, the plastering works started on the 3rd floor and the execution of the sanitary installations on the same floor continues. The construction of the electrical installations reached level 4, where the screed casting and helicoptering process also took place. At the same time, the installation of underfloor heating systems has reached the 3rd floor.

This month, plasterwork for the 2nd floor finished and continued for the 3rd floor at Cosmopolit no. 7 Traian Grozăvescu building site. The fitting of sanitary fixtures reached the 3rd floor, while work on the electric wiring progressed up to the 4th floor. Double pane windows were mounted on the 6th floor and necessary action was taken for the connection to the gas pipeline grid.

At building site Cosmopolit Traian Grozavescu, plastering work for the first floor has been completed this month, with work for the second floor in progress. Fitting of the electric wiring and sanitation appliances reached the fourth floor, while insulated glaze-windows windows are currently being fitted on the fifth floor.

First floor plastering started in February on building site Traian Grozavescu, while the fitting of floor heating systems and pouring of specific slabs continued.

Electric wiring is being fitted on the 3rd floor and masonry work on the 6th floor is almost finished.

In the first half of the month, work on the electric wiring for the 2nd floor continued and the installation and connection of the sanitary fixtures for the 3rd floor advanced.

Furthermore, masonry work for the 4th and 5th floors continued and the fitting of the double glazed window for the 3rd floor was initiated.

In the second half of January, work on the electrical wiring and sanitary fixtures for the second floor continued and the fitting of the floor heating systems for the 1st floor started.

In the same interval, the fitting of the double glazed windows for the 3rd floor ended, and fitting of double glazed windows for the 4th floor started, while masonry work for the 4th and 5th floors continued.

The slab on the last floor of the building (6th) was stripped in December, and with this stage, structural works finalised. Masonry work continued for the 4th and 5th floors, and simultaneously works on the electric wiring and the installation and connection of sanitary fixtures commenced on the 1st and 2nd floor.

Equally, the fitting of the double glazed windows commenced for the 1st and 2nd floors.

At Cosmopolit Traian Grozavescu, the start of November was marked by extensive structural work on the 6th floor, as well as by the process of pouring the concrete diaphragm and poles for this storey. At the same time, casing and reinforcement work for the flooring has started.

As for the masonry, simultaneous work is underway on the second, third and fourth floors, while on the ground floor, the installation of the electric network has started.

In the second half of November at building site Traian Grozavescu 7, the floor slab over the 6th floor was cast while work of encasing, reinforcement and associated parapets casting continued.

Masonry work started for the 5th floor and electric wiring for the 1st floor continued.

The plate was poured in October over the 4th floor and we started shuttering, reinforcement and casting of columns on this floor.

We also continue with the interior masonry works on the 1st and 2nd floors.

Work of casting, reinforcing, alongside diaphragm concrete and pole pouring for the fifth floor have been underway during the second half of October. Furthermore, the floor for the same storey was reinforced.

At the same time, masonry work for the second floor has also continued.

First floor masonry 1st + beam over 3rd

Structural frame work advances on the Traian Grozavescu Cosmopolit building site and work of reinforcement, encasing and pouring of the beam for the second floor are underway. Masonry work for ground floor business premises and offices started. Work for the electric wiring and sanitary fixtures for basement S1 and S2 advances.

Work for encasing, reinforcement and pouring the beam over the first floor continue. Simultaneously, the masonry work for basement 1 is achieved.

Work for pouring the ground floor beam and construction of the ground floor beam finish. Work starts on fixtures for exterior installations.

Work of encasing, reinforcement and pole pouring for the ground floor, alongside encasing and reinforcement of the ground floor beam continue at building site Cosmopolit Traian Grozăvescu 7. Also, work for the electric wiring and sanitary fixtures for basement S1 and S2 advance.

Work within project Cosmopolit Traian Grozăvescu 7 is progressing. In April, work of encasing, reinforcement and pouring of poles and walls for the ground floor continues. Simultaneously, necessary actions for electric wiring and sanitary fixtures for basement 2 are underway.

Work of encasing, reinforcement and pouring of vertical elements at the level of basement 1 are underway, following that until the end of the month, encasing, reinforcement and pouring of vertical elements at the level of basement 1 is achieved.

Work on the framework and reinforcement for the main and secondary beams and for partition walls and support poles for basement 2 continues. Reinforcement, encasing and slab pouring work for basement 2 are achieved.

Building work for Cosmopolit Traian Grozăvescu 7 advances steadily. Reinforcement of partition walls and support poles for basement 2 starts.

Work on the grade beam footing ends and the foundation of the building is poured.

Work on the grade beam footing starts.

Foundation digs start and the foundation for the two cranes on site is poured.

Foundation digs start in June.

Demolition and clearance work continue on building site Cosmopolit Traian Grozăvescu 7.

Demolition works for the new residential project Cosmopolit Traian Grozăvescu 7 start in May 2019.